Day 31 (Dec 3, 2011) 

Removed T-5 Transmission and installed the Turbo 350. 

 Day 32 (Dec 4, 2011) 

 Fabricated front body mounts. Worked on floor over transmission tunnel and right foot well.

Day 33 (Dec 18, 2011)  

Moved Lark out onto pad. 

Day 34 (Sep 3, 2012)  

Moved Lark back into garage and started working in the driveshaft tunnel. 

 Day 35 (Sep 7, 2012) 

Worked on driveshaft tunnel and floor